Question 1.

The normal time required for the completion of project in the above problem is

A.

 9 days

B.

 13 days

C.

 14 days

D.

 19 days

Explanation :

Explanation Not Provided

Question 2.

If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be

A.

 to + 3tm+ tp/3

B.

 to + 4tm+ tp/4

C.

 to + 4tm+ tp/5

D.

 to + 4tm+ tp/6

Explanation :

Explanation Not Provided

Question 3.

A construction schedule is prepared after collecting

A.

 Number of operations

B.

 Output of labour

C.

 Output of machinery

D.

 All the above

Explanation :

Explanation Not Provided

Question 4.

If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively

A.

 3.5 and 5/6

B.

 5 and 25/36

C.

 3.5 and 25/36

D.

 4 and 5/6

Explanation :

Explanation Not Provided

Question 5.

Bar charts are suitable for

A.

 Minor works

B.

 Major works

C.

 Large projects

D.

 All the Above

Explanation :

Explanation Not Provided