Question 16.

The measurement is made in square metre in case of

A.

 Cement concrete in foundation

B.

 R.C.C. structure

C.

 Hollow concrete block wall

D.

 None of these

Explanation :

Explanation Not Provided

Question 17.

The measurement is made for stone work in square metre in case of

A.

 Wall facing

B.

 Columns, lintels, copings

C.

 Building work

D.

 (A) and (B) of the above

Explanation :

Explanation Not Provided

Question 18.

As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken

A.

 1.80 liters for 5 to 10 users

B.

 1.20 liters for 15 users

C.

 1.35 for 20 users

D.

 All the above

Explanation :

Explanation Not Provided

Question 19.

Pick up the correct statement in case of water supply.

A.

 Pipes laid in trenches and pipes fixed to walls are measured separately

B.

 Cutting through walls and floors are included with the item

C.

 Pipes are classified according to their sizes and quality

D.

 All the above

Explanation :

Explanation Not Provided

Question 20.

The cost of the earthwork in excavation for the surface drain of cross-section shown in the given figure for a total length of 5 metres @ Rs. 450% cum, is

A.

 Rs. 400

B.

 Rs. 425

C.

 Rs. 450

D.

 Rs. 500

Explanation :

Explanation Not Provided